CEMENT DEEP MIXING(CDM) WORKS FOR PATIMBAN PORT DEVELOPMENT PROJECT (1-2) PACKAGE 6 CONTAINER TERMINAL NO.2
|
PTRPWJ (PENTA OCEAN-TOYO-RINKAI-PP-WIKA-JAKON) |
DGST |
2023-05-01 |
2024-04-05
| 10,666,326 USD
| INDONESIA |
MARINE DCM |
Marine Cement Deep Mixing(CDM) Works For PATIMBAN PORT DEVELOPMENT PROJECT (II) PACKAGE 5 CAR TERMINAL
|
TWWHA JO (TOA-WASKITA-WAKACHIKU-HUTAMA-ABIPRAYA JO |
DGST |
2023-02-07 |
2024-04-06
| 26,451,167 USD
| INDONESIA |
MARINE DCM |
Cross Island CR102 (Design and Construction of Tunnel between Aviation Park Station and Depot) - Gro
|
Shanghai Tunnel Eng. - LT SAMBO JV |
Land Transport Authority |
2022-06-01 |
2024-07-31
| 39,729,192 USD
| SINGAPORE |
DSM |
CONTRACT 3206 - MAIN RECLAMATION WORKS (SPECIALIST SUB-CONTRACT FOR LAND DCM WORKS)
|
PHKL |
AIRPORT AUTHORITY HONG KONG |
2019-08-12 |
2019-01-31
| 16,676,660 USD
| HONGKONG |
DCM |
CONSTRUCTION OF POLDER AT AREAS A AND C OF PULAU TEKONG(PVD)
|
HDB (Housing & Development Board) |
Boskalis Penta-Ocean Joint Venture |
2018-12-01 |
2023-04-18
| 9,529,572 USD
| SINGAPORE |
PVD |
CONTRACT 3206 - MAIN RECLAMATION WORKS (SPECIALIST SUB-CONTRACT FOR MARINE DCM WORKS)
|
PHKL |
AIRPORT AUTHORITY HONG KONG |
2018-06-17 |
2019-01-31
| 16,677,000 USD
| HONGKONG |
MARINE DCM |
THREE RUNWAY SYSTEM PROJECT CONTRACT 3203-DEEP CEMENT MIXING WORKS(PACKAGE3)
|
SAMBO E&C |
AIRPORT AUTHORITY HONG KONG |
2016-08-10 |
2018-03-10
| 56,355,000 USD
| HONGKONG |
MARINE DCM |
THREE RUNWAY SYSTEM PROJECT CONTRACT 3201-DEEP CEMENT MIXING WORK-PACKAGE1
|
PENTA-OCEAN CONS |
AIRPORT AUTHORITY HONG KONG |
2016-08-01 |
2018-01-28
| 52,784,000 USD
| HONGKONG |
MARINE DCM |
LAND PREPARATION WORKS(INSTALLATION OF PREFABRICATEF VERTICAL DRAINS) FOR AIRPORT DEVELOPMENT
|
PENTA-OCEAN J/V |
MINISTRY OF TRANSPORT |
2014-10-23 |
2020-08-22
| 12,862,000 USD
| SINGAPORE |
PVD |
CONTRACT T228 CONSTRUCTION OF GARDENS BY THE BAY STATION AND TUNNELS FOR THOMSON LINE-GROUND IMPROVEMENT WORKS
|
KKL |
LAND TRANSPORT AUTHORITY |
2014-10-08 |
2016-04-07
| 9,802,000 USD
| SINGAPORE |
"DSM, JGP" |
MARINE CONSTRUCTION WORKS FOR NGHI SON REFINERY AND PETROCHEMICAL COMPLEX PROJECT
|
SK ENGINEERING & CONSTRUCTION CO.,LTD |
NGHI SON REFINERY AND PETROCHEMICAL |
2013-12-17 |
2016-06-30
| 14,475,000 USD
| VIETNAM |
ROCK SUPPLY,DREDGING |
MUBARAK AL-KABEER SEAPORT PROJECT(PHASE 1- STAGE 1)
|
HYUNDAI ENGINEERING & CONSTRUCTION CO.,LTD |
MINISTRY OF PUBLIC WORKS |
2013-02-01 |
2013-10-31
| 7,450,000 USD
| KUWAIT |
BAND DRAIN |
HANOI-HAIPHONG EXPRESSWAY PROJECT PACKAGE-4
|
KEANGNAM ENTERPRISES.,LTD |
VIETNAM INFRASTRUCTIVE DEVELOPMENT AND FINANCE INVESTMENT JOINT STOCK COMPANY |
2011-12-12 |
2013-06-30
| 7,623,000 USD
| VIETNAM |
PBD |
JURONG AROMATICS COMPLEX PROJECT
|
SK ENGINEERING & CONSTRUCTION CO.,LTD |
"JURONG AROMATICS CORPORATION PTE. LTD" |
2011-10-31 |
2012-07-15
| 10,627,000 USD
| SINGAPORE |
PILE |
PILE DRIVING FOR CAI LAN INTERNATIONAL CONTAINER TERMINAL C1000-MARINE WORK
|
HALLA E&C |
CAI LAN INTERNATIONAL CONTAINER LLC. |
2011-07-01 |
2013-08-29
| 7,716,000 USD
| VIETNAM |
PILE |
BOUBYAN SEAPORT PROJECT IN KUWAIT
|
HYUNDAI ENGINEERING & CONSTRUCTION CO.,LTD |
MINISTRY OF PUBLIC WORKS |
2011-06-11 |
2012-02-09
| 13,629,000 USD
| KUWAIT |
MARINE DSM |
DOWN TOWN LINE CONTRACT 915
|
SK ENGINEERING & CONSTRUCTION CO.,LTD |
LAND TRANSPORT AUTHORITY |
2010-05-01 |
2013-03-31
| 8,937,000 USD
| SINGAPORE |
BOARD PILE |
PACKAGE EX-7 UNDER THE HANOI-HAIPONG EXPRESSWAY PROJECT
|
GS ENGINEERING & CONSTRUCTION CORP., |
VIETNAM INFRASTRUCTIVE DEVELOPMENT AND FINANCE INVESTMENT JOINT STOCK COMPANY |
2009-05-01 |
2014-02-26
| 9,416,000 USD
| VIETNAM |
PVD |
DESIGN, CONSTRUCTION AND COMPLETION OF MARINA COASTAL EXPRESSWAY, CONTRACT 487(ECP/LPE INTERCHANGE)
|
DAELIM INDUSTRIAL CO.,LTD |
SINGAPORE LAND TRANSPORT AUTHORITY |
2009-03-01 |
2011-12-31
| 23,421,000 USD
| SINGAPORE |
LAND DSM & JGP |
TUAS Power Station A Fuel Oil Tank 설치용 기초토목(Bored Piling)공사
|
Doosan Heavy Industries & Construction Co., Ltd. |
MINISTRY OF TRADE & INDUSTRY |
1997-04-01 |
1997-11-30
| 10,305,960 USD
| SINGAPORE |
BOARD PILE |