    Chosuk HD is a specialized company in soft ground improvement, with accumulated construction methods and know-how since 1970.

    Construction Method

    Chosuk HD is a specialized company in soft ground improvement, with accumulated construction methods and know-how since 1970.

    Offshore Sand Compaction Pile

    페이지 정보

    본문

    Subsea Soft Ground Replacement Method



    1. Method Overview


    1) Ground improvement method that creates large-diameter compacted sand columns on the soft ground of the seabed. 2) Improvement effects

      ① Sandy soil

       - Prevents liquefaction during earthquakes and ground motions

       - Increases horizontal load (increases shear strength)

       - Reduces compressive settlement

       - Homogenization of the ground by compaction

      ② Clayey soil

       - Increases shear resistance and bearing capacity by forming a composite ground

       - Prevents sliding destruction

       - Shortens consolidation time and reduces consolidation settlement (DRAIN effect)

       - Prevents uneven settlement with the composite ground function

    3) Applicability

       Applicable to almost all grounds such as sandy soil, clayey soil, organic soil, rocky soil (landfill), and sedimentary soil



    2. Construction method features


    1) Compaction, reinforcement, and drainage promotion

    2) Increases shear strength

    3) Prevents liquefaction

    4) Shortens air time

    5) Increases bearing capacity

     


    3. Construction method and sequence

    0c8802f0380c192bb46616454d28d4f3_1725770269_8622.png


    1) Fixing the location

    2) CASING penetration: Automatic air control device operation 3) CASING pull-out

    4) CASING compaction

    5) When compaction is complete, pull-out as in method 3)

    6) Work as in method 4)

    7) Repeat methods 3), 4), 5), and 6) from the support layer to the ground surface (planned depth).

    8) Work completion